From Foshan factory floor to hotel loading dock worldwide — we manage the entire logistics chain: export packaging, cargo consolidation, documentation, ocean freight booking, and customs coordination with full DDP transparency.
Send a BOQ, drawing set or specification. You get a costed response, or the questions needed to produce one.
Transit time is the variable buyers most often under-estimate. These are the typical consolidated shipping figures for FF&E containers out of Foshan / Nansha.
| Item | Typical Figure |
|---|---|
| Containers for a 300-room package | 15–25 containers |
| Consolidation loading window | 3–5 days, single booking |
| Ocean transit — UAE (Jebel Ali) | 18–30 days |
| Ocean transit — Saudi Arabia (Dammam / Jeddah) | 22–35 days |
| Ocean transit — US East Coast | 30–40 days |
| Ocean transit — US West Coast | 22–32 days |
| Ocean transit — UK & Northern Europe | 30–40 days |
| Ocean transit — Australia | 18–28 days |
| Customs clearance & final-mile delivery | 5–10 working days |
| Shipping terms | FOB, CIF or DDP |
| Quotation turnaround | Within 5 business days |
Ranges are typical for consolidated orders produced across the Foshan partner network. Stage-by-stage detail: FF&E Lead Times 2026 · What an FF&E Package Includes.
Damage in an FF&E shipment is rarely caused by the ocean leg. It is caused by how the goods were packed at the factory and how they were loaded into the container, and both of those are decided weeks before the vessel sails. The table below is the packing specification we apply by default. It is not a sales sheet — it is what the factory is instructed to do, and what the loading photos are checked against before the container is sealed.
| Category | Packing | Loading note |
|---|---|---|
| Casegoods | EPE foam wrap on all edges and corners, 5-layer corrugated carton, corner protectors on every carcass | Flat-packed carcasses where the design allows; assembled units need a wider footprint and cost roughly 20% more container space |
| Upholstered seating | Foam corner blocks, stretch wrap, breathable bag — never vacuum-sealed for more than 14 days | Bags are opened on arrival for inspection; long transit in sealed plastic traps moisture and sets creases in the cover |
| Marble and stone tops | Foam-faced A-frame crate, tops stood on edge, never stacked flat | Stacking flat is the single most common cause of transit breakage on stone tops |
| Glass and mirrors | Timber crate with foam spacers, individual cardboard sleeves, vertical orientation only | Marked fragile and loaded last so nothing sits on top of the crate |
| Fixed joinery | Disassembled into panels, panel edges banded, hardware bagged and labelled per unit | Labelled by room number and unit so the installation crew can work room by room |
| Lighting and hardware | Individual cartons inside a master carton, anti-static wrap on drivers and LED boards | Kept off the container floor and away from doors — the two places that take water |
| Mattresses | Vacuum-compressed and rolled, boxed individually | Recovers to full height within 48–72 hours of unboxing; do not open before the room is ready |
Consolidation is where the cost actually moves. Goods from five factories arriving at the port on five different dates will either wait for each other or ship separately, and both outcomes cost money. We hold the schedule, book the container against the slowest factory rather than the fastest, and issue loading photographs and a sealed container number before the bill of lading is released. Send the FF&E schedule with destination port and required on-site date, and the loading plan comes back with a container count and a sailing window.
Two photographs come back per container before the doors are shut: the load as it stands, and the door end once it is braced. The first is checked against the packing list, the second against the loading plan. Both go out the same day with the container number and the seal number, and the shipment is signed off against them.
Share project scope, destination, and timeline — receive a tailored quotation from Foshan within 5 business days.
Get a Shipping & Logistics QuoteWe offer FOB, CIF, and DDP shipping terms. For full container loads (FCL), we ship directly from Foshan/Nanhai ports to destination ports worldwide. For smaller orders, we offer LCL consolidation with other project items.
We provide complete customs documentation including commercial invoice, packing list, bill of lading, certificate of origin, and all required compliance certificates. HS codes are clearly declared for each product category.
A 300-room hotel FF&E package covering casegoods, soft seating, dining furniture, lobby pieces and bathroom vanities consolidates into 15-25 containers, loaded inside a single 3-5 day window so the whole package moves on one booking. Ocean transit from Foshan / Nansha is 18-30 days to Jebel Ali, 22-35 days to Dammam or Jeddah, 30-40 days to the US East Coast, 22-32 days to the US West Coast, 30-40 days to the UK and Northern Europe, and 18-28 days to Australia. Customs clearance and final-mile delivery add 5-10 working days.