A 200m² boutique café-restaurant in central London — fully furnished from a single source. 15 product categories delivered in 2 containers within 8 weeks, meeting BS 5852 Crib 5 fire compliance for all upholstered items.
Who delivered this: production ran at a partner factory in our Foshan network — an independent facility we do not own. FoshanFFE carried the BOQ consolidation, in-process and pre-shipment inspection, documentation and freight. Figures below are the commercial basis of the package as quoted.
Key parameters at a glance.
| Location | Central London, United Kingdom |
|---|---|
| Project Type | New-build boutique café-restaurant (ground floor + mezzanine) |
| Floor Area | 200m² (ground floor + mezzanine) |
| Seating Capacity | 65 seats (ground floor 45 + mezzanine 20) |
| Product Categories | 15 — booth seating, dining tables, bar counter, café station, pendant lighting, floor tiles, wall cladding, fixed millwork, signage hardware |
| Fire Compliance | BS 5852 Crib 5 (all upholstered seating), BS 7176 medium hazard |
| Lead Time | 8 weeks (design approval to container loading) |
| Shipping | 1 × 40HQ + 1 × 20GP, FOB Nansha/Guangzhou |
| FOB Value | ~$85,000 USD |
A London-based restaurant group opened a new boutique café-restaurant concept in a converted Victorian building in central London. The space — 200m² across ground floor and mezzanine — required a complete FF&E package spanning 15 distinct product categories. Rather than coordinating 8–10 separate suppliers (furniture, lighting, tiles, cladding, millwork, signage...), the owner chose a single integrator to manage the entire scope on one purchase order.
The design called for a warm industrial aesthetic: exposed steel frames, emerald green velvet booth seating, walnut dining tables, a curved GFRC (glass-fibre reinforced concrete) bar counter, and pendant lighting with brass finishes. Every element had to work together as a cohesive visual language while meeting strict UK fire safety regulations for commercial dining spaces.
Two constraints shaped the project: an 8-week timeline from design approval to container loading (driven by the building's construction schedule), and London's nighttime delivery restrictions for the installation phase. Central London's congestion zone limits commercial vehicle access to specific hours, requiring precise coordination between shipping schedule and the site's installation crew.
Every element of the dining experience, from seat to signage.
The restaurant group was accustomed to managing multiple specialist suppliers. Consolidating 15 product categories — spanning furniture, metalwork, concrete, lighting, tiles, and millwork — into a single PO with one delivery date was a significant coordination challenge.
SolutionActivated the 19-partner Foshan production network. Furniture produced in-house, GFRC outsourced to a specialist concrete fabricator, brass lighting sourced from a dedicated metal workshop, porcelain tiles from a Guangdong ceramic factory. All items converged at the consolidation warehouse, packed into 2 containers on a synchronized 8-week schedule. Zero items missed the loading window.
The designer specified sweeping S-curve booth seats with precise radii (1800mm arc, R600mm inner curve). Achieving this geometry in plywood shell construction while maintaining Crib 5 fire compliance required careful prototyping.
SolutionBuilt 2 full-scale booth prototypes in week 1, shipped air-freight to London for designer review. Approved with one minor radius adjustment (R600→R550mm). Final production used CNC-cut plywood shells with FR-treated foam and velvet upholstery. All 6 units passed BS 5852 Crib 5 on first test.
Central London's congestion zone restricts commercial vehicle access. The installation crew could only receive deliveries between 20:00–06:00, and the building's neighbors enforced strict noise limits after 22:00.
SolutionPre-labeled every crate with room-zone code and installation sequence number. Provided the London crew with a detailed floor-plan showing exact placement positions. Container arrival was timed for 19:30, allowing the crew to begin unloading at the 20:00 window. All installation completed within 3 night shifts — no noise complaints, no delays.
8 weeks from design approval to container loading.
| Week | Milestone | Status |
|---|---|---|
| Week 1 | Design review & prototype booth | 2 booth prototypes built, air-freighted to London |
| Week 2 | Prototype approval & material ordering | R550mm radius approved, all raw materials ordered |
| Week 2–5 | Furniture production | 56 seating units + 16 tables produced |
| Week 3–5 | Bar counter & café station | GFRC fabrication, granite top polishing |
| Week 4–6 | Lighting & tiles | 21 lighting fixtures, 200m² porcelain tiles packaged |
| Week 6–7 | Wall cladding & millwork | 85m² slat panels, fixed millwork produced |
| Week 7 | BS 5852 Crib 5 testing | 3 upholstery types tested at SGS, all passed |
| Week 8 | Consolidation & loading | 1×40HQ + 1×20GP loaded, customs cleared |
Yes. The 19-partner Foshan production network covers furniture, metalwork, concrete, lighting, ceramics, and millwork. All categories consolidated at one warehouse and shipped in one or two containers — single PO, single delivery.
Yes. Full-scale prototypes are built using CNC-cut plywood shells to match any curve or radius. Prototypes can be air-freighted for client review before mass production. Fire compliance (BS 5852, EN 1021) is maintained across all custom shapes.
Projects from $50K to $3M FOB are regularly handled. Even smaller projects like a 200m² café benefit from the consolidation model — 15 categories on one PO means one quality standard, one delivery schedule, and one point of accountability.
Share your floor plan, design concept, and opening timeline — the team will respond with a complete FF&E proposal covering all categories on one PO.