Millwork fails for one reason more often than any other: the thing that got built was not the thing that got approved. This page covers what counts as millwork, how the drawing chain is controlled, where tolerances are won or lost, and what we need in order to price it.
Send the joinery details, elevations and finish schedule. If only design intent exists, send that and we will tell you what the shop drawing stage will change.

Partner facility, Foshan. Millwork is fabricated at independent partner workshops; we hold the drawing chain, the inspection and the delivery.
Custom hotel millwork is the joinery built to the room rather than bought for it: reception desks, back bars, wardrobes, vanities, headboard walls, corridor and lift-lobby panelling, banquettes and fixed seating.
The value we add is not the saw. It is the drawing chain: one approved revision, one mockup, one inspection standard, one party answering when the fitted item does not meet the wall.
Seven categories cover most of a hotel package. Each has a different failure mode, so each is inspected differently.
Curved or faceted, cable management, transaction top, staff-side storage. Failure mode: substrate movement at the curve.
Glass display, undercounter refrigeration housings, wet-zone sealing. Failure mode: moisture ingress at the counter joint.
Hanging, shelving, safe housing, sliding or hinged fronts. Failure mode: door alignment after the first season.
Wall-hung or floor-standing, stone top, plumbing cut-outs. Failure mode: unsealed core swelling at the wet edge.
Upholstered or timber, integrated lighting, acoustic backing. Failure mode: fixings that cannot be re-tensioned.
Room-number surrounds, niche shelving, protective skirting. Failure mode: impact damage at trolley height.
Framed, upholstered, built to the booth dimension. Failure mode: foam collapse at the front edge.
Every gate has an owner and an output. When a millwork item arrives wrong, it is almost always because a gate was skipped rather than because a factory made a mistake.
| Gate | What happens | Who signs | Output that must exist |
|---|---|---|---|
| 1. Design intent | Designer issues the FF package, elevations and finish schedule | Designer | Drawing set with revision number |
| 2. Shop drawing | Factory drafts constructible details: sections, substrate, fixings, joints | Factory + us | Shop drawing set, RFI list |
| 3. Review and approval | Designer and brand review; comments closed; revision frozen | Designer / brand | Stamped approval naming the revision |
| 4. Mockup | One representative unit built and inspected in the finish | Designer + us | Mockup acceptance note, photo record |
| 5. Production | Fabrication against the frozen revision, in-process checks at fixed points | Factory + our QC | In-process records, material certificates |
| 6. Fit and snag | Site fit-up, scribe to the actual wall, snag list closed | Installer + us | Snag list, close-out photos |
These eight lines are the ones we will not leave to a verbal agreement. Each is written into the shop drawing before fabrication.
| Item | What we hold | Why |
|---|---|---|
| Panel thickness | 18mm nominal for carcasses, 25mm for work surfaces | Below this, spans sag |
| Wall straightness | Scribe allowance of 10mm minimum at every wall-fixed item | No site wall is square; a scribe detail absorbs it |
| Floor level | Adjustable feet or plinth with 15mm levelling range | Screeds are never flat |
| Door reveal | 2–3mm consistent reveal, self-closing hardware above 1,200mm height | Reveal drift is the first thing an auditor photographs |
| Edge sealing | All six faces sealed on moisture-exposed items | Unsealed core is a one-season failure |
| Fixings | Through-bolted to blocking, anti-tip where free-standing | Guest safety, not aesthetics |
| Fire and smoke | Fire-rated door sets and intumescent where the compartment requires it | A joinery package cannot break a fire strategy |
| Finish and sheen | Agreed sheen level per surface, sample-approved | Sheen mismatches read as defects in photos |
The most common cause. It is not a factory problem and it is not solved by remaking the item.
On refurbishment, existing walls, floors and services must be measured before the shop drawing is frozen.
Sockets, data, drainage and lighting cut-outs land inside a panel unless they are drawn on the joinery elevation.
A wardrobe that cannot enter the room because the door casing went in first is a site planning failure.
| Stage | Duration | Clock starts when |
|---|---|---|
| Shop drawing and RFI | 7–12 days | Design intent and finish schedule received |
| Sample or mockup | 10–15 days | Shop drawing approved |
| Production | 50–65 days | Mockup accepted and PO released |
| Inspection and packing | 5–8 days | Production complete |
| Sea freight | 25–30 days to Jebel Ali 30–40 days to EU / NA |
Container sealed |
Millwork carries one extra stage compared with loose furniture, and that stage is the one most schedules forget to allow for.
Loose furniture arrives finished and gets placed. Custom millwork is built to the room: it is drawn, approved, fabricated and often fitted on site. Reception desks, back bars, wardrobes and wall panelling are millwork. A nightstand is furniture, unless it is built into the wall.
On a new build we work from the architectural drawings and flag every dimension that depends on a site condition. On a refurbishment we ask for site measurements before fabrication, or build in a tolerance allowance with a scribe detail. A millwork item that assumes a square wall is a rework order.
Yes, and on anything above a few units we recommend it. A mockup room or a single representative unit lets the designer, the brand and the contractor agree on the detail before the production run.
The FF package or joinery details, the room elevations, the finish schedule and the hardware spec. If only a design intent package exists, we can quote against it with the understanding that the shop drawing stage will move the number.
Send the joinery details, elevations and finish schedule. We come back with a scope split, the RFI list, and the drawing revision we will build to.
Submit Your BOQ